WEST OLIVE, Mich. — The J.H. Campbell coal plant on the Lake Michigan shore in Ottawa County will keep running into the new year after the U.S. Department of Energy issued a seventh emergency order blocking its retirement.
The newest order, numbered 202-26-51 and issued under Section 202(c) of the Federal Power Act, took effect Sunday, Nov. 15, and lasts through Feb. 12, 2027. It directs the regional grid operator, the Midcontinent Independent System Operator, to work with Consumers Energy so the plant stays available, and tells the operator to run it on economic dispatch only during the hours an emergency requires.
The previous order was due to lapse Saturday, and federal officials renewed it late Friday.
Energy Secretary Chris Wright argued in a Nov. 14 statement that keeping coal units such as Campbell available has headed off blackouts. The department pointed to a joint federal reliability review of last winter’s Arctic cold stretch, including Winter Storm Fern, as evidence the region needs power plants that can be dispatched on demand.
Campbell is the last coal plant Consumers Energy operates. It had been scheduled to shut down on May 31, 2025, roughly 15 years ahead of the end of its design life, until federal orders began keeping it online weeks before that date.
The cost question is what reaches Michigan households. Consumers Energy has asked to recover the expense of keeping the plant open, which would flow to its customers through higher rates. The Michigan Attorney General’s office put the added operating cost at $295 million as of September.
Michigan sued to overturn the orders, and in September a federal judge ruled the department had gone beyond its legal authority. The Energy Department is appealing that ruling. Attorney General Dana Nessel has called the plant one that nobody asked to keep and said ratepayers are being stuck with the bill.